Cobot cell that sorts samples into trays
A table-mounted collaborative robot that picks sample tubes from a rack and sorts them into trays by label.
- Delivered in
- 25 business days
- One price
- EUR 45,181.0
- Positions
- 7
- Suppliers asked
- 10
From request to delivery in 25 business days
From request to delivery, day by day: quotes come in, the best option is ordered, parts travel to the assembler, then assembly, test and delivery. Click anywhere to pause. Example figures, not a quote.
The request
A small robot cell for our lab that takes sample tubes from a rack and sorts them into trays, safe to work next to.
The draft
A collaborative robot arm with a two-finger gripper on a steel table with a machined top plate. Fixtures hold the rack and the trays in fixed positions. A camera reads the labels. Delivered assembled, programmed for the sorting task and tested on site.
Technical drawing
Example drawing with design values from the draft, not for manufacture. The numbers in the balloons are the positions in the plan below.
Plan and quotes
Every position with its route, the suppliers asked and what they quoted. Example figures, not a quote.
| No | Part and route | Estimate | Opt | Supplier | Price source | Time | Price |
|---|---|---|---|---|---|---|---|
| 01 | Robot armCollaborative robot from a catalogue | 10 d EUR 24,500 | Universal RobotsUR5e (reseller Wired Workers), net VAT, source, checked 2026-11-13 | Catalogue | ~10 d | EUR 30,619.0 | |
| 02 | GripperCatalogue end-of-arm tool | 8 d EUR 3,900 | OnRobotOnRobot 2FG7 (reseller Unchained Robotics), net VAT, source, checked 2026-11-13 | Catalogue | ~8 d | EUR 4,078.0 | |
| 03 | Table frameLaser-cut and bent steel2 alternatives | 6 d EUR 850 | A | 247TailorSteel | Quote | 6 d | EUR 850 |
| B | pewag engineering | Quote | 5 d | EUR 952 | |||
| 04 | Top plate and fixturesCNC-milled aluminium2 alternatives | 8 d EUR 1,400 | A | Milltech | Quote | 8 d | EUR 1,400 |
| B | MakerVerse | Quote | 10 d | EUR 1,320 | |||
| 05 | Label cameraCatalogue part | 5 d EUR 900 | BaslerBasler ace acA1920-40uc Color USB 3.0 Camera (Edmund Optics, stock #33-981), net VAT, source, checked 2026-11-13 | Catalogue | ~5 d | EUR 610.0 | |
| 06 | Integration, programming and testSpecial machine builder2 alternatives | 10 d EUR 7,800 | A | Moehle Maschinenbau | Quote | 12 d | EUR 7,254 |
| B | Kluger-Prokutec Sondermaschinenbau | Quote | 10 d | EUR 7,800 | |||
| 07 | Delivery and installationFreight transport | 2 d EUR 450 | zipmend Express | Quote | 2 d | EUR 450 | |
| Total, best value per line | 25 business days, EUR 45,181.0 | ||||||
Green lowest price or fastest, red highest or slowest among alternatives, shaded row best value (price and time weighed).
How to read this table
Best value weighs price and time: a saved business day counts as 3% of the cheapest quote, so a slightly dearer but quicker quote can win. Catalogue prices are published list prices from the named source, so VAT status varies; their time is the line estimate. Red lines have no price yet. Quotes, then parts run in parallel, then assembly and transport. Production sites are city-level.
Shipments on the map
| Shipment | From | To | Time |
|---|---|---|---|
| Robot arm | Universal Robots, Odense | Moehle Maschinenbau | day 7 to 11 |
| Gripper | OnRobot, Odense | Moehle Maschinenbau | day 5.8 to 9 |
| Table frame | 247TailorSteel, Varsseveld | Moehle Maschinenbau | day 4.6 to 7 |
| Top plate and fixtures | MakerVerse, Berlin | Moehle Maschinenbau | day 7 to 11 |
| Label camera | Basler, Ahrensburg | Moehle Maschinenbau | day 4 to 6 |
| Delivery and installation | Moehle Maschinenbau, Hessisch Oldendorf | Munich | day 23 to 25 |